10-Stage EWI Photo Checklist Template
Capturing verified stage photographs is mandatory for NSAI Agrément audit folders and SEAI Better Energy Homes grant sign offs. This 10 stage checklist gives site managers and installers the exact inspection criteria required for every elevation before subsequent system coats conceal critical structural fixing and weatherproofing details.
Download Printable PDF Checklist
Enter your professional work email to download the high resolution printable inspection checklist.
Printable 10-Stage Inspection Table
Use this reference table on site to verify photographic milestones before proceeding to next coats.
| Stage | Milestone Title | Required Photographic Evidence | Acceptance Criteria | Verified |
|---|---|---|---|---|
| 01 | Pre Installation Survey | Four full property elevations, spalling masonry, damp patches, service pipes. | Existing substrate defects marked and resolved prior to board fixing. | [ ] Pass |
| 02 | Substrate Pull Off Tests | Tensile tester attached, gauge reading in kN/m2, substrate failure surface. | Cohesive failure of substrate or adhesive exceeding manufacturer minimum. | [ ] Pass |
| 03 | Base Track & Starter Profile | Laser level alignment, 150mm ground clearance, fixings at 300mm centres. | Track level within 2mm over 2m, expanding seal tape installed behind profile. | [ ] Pass |
| 04 | Adhesive Application Pattern | Reverse side of slab showing continuous perimeter strip plus internal adhesive dabs. | Minimum 40 percent adhesive surface coverage after slab compression. | [ ] Pass |
| 05 | Board Layout & Stagger | Full elevation showing brick bond stagger pattern and interlocked building corners. | Minimum 200mm vertical joint stagger, no L shaped cutout joints at corners. | [ ] Pass |
| 06 | Mechanical Fixings Pattern | Anchor density across elevation, close up of countersunk head and insulation plug. | Fixing density meets wind load design (typically 5 to 8 per m2), flush or plugged. | [ ] Pass |
| 07 | Corner & Opening Stress Mesh | Diagonal 45 degree reinforcement patches (200x300mm) at all window and door corners. | Patches bedded into basecoat prior to applying main elevation mesh. | [ ] Pass |
| 08 | Basecoat & Mesh Overlap | Main mesh application with measuring tape showing minimum 100mm overlap. | Mesh embedded in upper third of basecoat, no direct contact with EPS slab. | [ ] Pass |
| 09 | Cill, Flashing & Mastic Seals | Oversill overhang (minimum 40mm projection), end cap seals, and mastic jointing. | Continuous hybrid polymer sealant bead around all window and door perimeters. | [ ] Pass |
| 10 | Topcoat Render & Handover | Finished elevation showing consistent texture, completed downpipes, site cleaned. | Uniform appearance without scaffold joint lines or surface blemishes. | [ ] Pass |