Free Downloadable Checklist

10-Stage EWI Photo Checklist Template

Capturing verified stage photographs is mandatory for NSAI Agrément audit folders and SEAI Better Energy Homes grant sign offs. This 10 stage checklist gives site managers and installers the exact inspection criteria required for every elevation before subsequent system coats conceal critical structural fixing and weatherproofing details.

Download Printable PDF Checklist

Enter your professional work email to download the high resolution printable inspection checklist.

Printable 10-Stage Inspection Table

Use this reference table on site to verify photographic milestones before proceeding to next coats.

StageMilestone TitleRequired Photographic EvidenceAcceptance CriteriaVerified
01Pre Installation SurveyFour full property elevations, spalling masonry, damp patches, service pipes.Existing substrate defects marked and resolved prior to board fixing.[   ] Pass
02Substrate Pull Off TestsTensile tester attached, gauge reading in kN/m2, substrate failure surface.Cohesive failure of substrate or adhesive exceeding manufacturer minimum.[   ] Pass
03Base Track & Starter ProfileLaser level alignment, 150mm ground clearance, fixings at 300mm centres.Track level within 2mm over 2m, expanding seal tape installed behind profile.[   ] Pass
04Adhesive Application PatternReverse side of slab showing continuous perimeter strip plus internal adhesive dabs.Minimum 40 percent adhesive surface coverage after slab compression.[   ] Pass
05Board Layout & StaggerFull elevation showing brick bond stagger pattern and interlocked building corners.Minimum 200mm vertical joint stagger, no L shaped cutout joints at corners.[   ] Pass
06Mechanical Fixings PatternAnchor density across elevation, close up of countersunk head and insulation plug.Fixing density meets wind load design (typically 5 to 8 per m2), flush or plugged.[   ] Pass
07Corner & Opening Stress MeshDiagonal 45 degree reinforcement patches (200x300mm) at all window and door corners.Patches bedded into basecoat prior to applying main elevation mesh.[   ] Pass
08Basecoat & Mesh OverlapMain mesh application with measuring tape showing minimum 100mm overlap.Mesh embedded in upper third of basecoat, no direct contact with EPS slab.[   ] Pass
09Cill, Flashing & Mastic SealsOversill overhang (minimum 40mm projection), end cap seals, and mastic jointing.Continuous hybrid polymer sealant bead around all window and door perimeters.[   ] Pass
10Topcoat Render & HandoverFinished elevation showing consistent texture, completed downpipes, site cleaned.Uniform appearance without scaffold joint lines or surface blemishes.[   ] Pass